Description
This is an individual homework. Include a problem statement with each problem.
1.(9 points) Create a linear schedule for the construction of a 15-mile-long gas pipeline. Use the attached template. Maintain a time buffer of at least 1 day and space buffer of at least 2 miles between activities.
Activity | (mile/day) |
Survey & layout | 3 |
Clear & grub | .75 |
Earthwork | .5 |
Subbase | 1 |
Base | 1.5 |
Paving | 3 |
Signage & striping | 5 |
2.(9 points) Refer to the Warehouse project in Chapter 22 that we scheduled in the computer lab. Set the project start date to the last Monday in October.Set the project baseline.The actual project start date was delayed three days for bad weather. After the late start, all activities have taken their original planned durations so the project is still three days behind schedule. Update Actual Start, Actual Finish, and % Complete for a progress report as of the 3rd Friday in November.Include a progress line. Print a Tracking Gantt chart showing the baseline and current schedules. Include an overall Warehouse, Exterior Phase, and Interior Phase summary tasks as shown in Figure 22.13. Include the columns below in your Tracking Gantt chart. Label the Gantt chart bars with Task Name on the left, % Complete on the right.
Task Name | Duration | Baseline Start | Early Start | Actual Start | % Complete |
Unformatted Attachment Preview
Purchase answer to see full attachment

Explanation & Answer

Thank you so much
Linear Schedule Template
1 2 3 4 5 6 7 8 9 #
11
12
13
14
15
16
17
18
19
20
21
0 1 2 3 4 5 6 7 8 9 #
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
...