The normal distribution revisited
UNIFORM DISTRIBUTION
(OVER A SPHERE)
The Normal Distribution
The Normal Distribution is perhaps the
most important distribution in probability
and statistics. It often arises in practice
due to a result in probability known as
“The Central Limit Theorem”, which
roughly states that sums and averages of
independent identically distributed
random variables tend to be normally
distributed.
© 2002 Thomson / South-Western
Slide 6-2
The Normal Distribution
For example, if “n” is large and “p” is “not
small”, then binomial (n, p)-distribution
can be approximated well by the normal
distribution with mean np and variance
np(1 – p).
© 2002 Thomson / South-Western
Slide 6-3
The Normal Distribution
A normal distribution is completely
characterized by its mean µ and standard
deviation σ and has the probability density
function given by:
1
−
2
x−
2
1
2 e
Where:
= mean of X
= standard deviation of X
= 3.14159 . . .
e = 2.71828 . . .
f ( x) =
© 2002 Thomson / South-Western
Slide 6-4
The Normal Distribution
Normal random variable is often denoted
as N(µ, σ). The probability density
function of normal distribution is bell
shaped and symmetric around its mean.
© 2002 Thomson / South-Western
Slide 6-5
The Normal Distribution
In applications, one is often interested in
computing the probability that a normal
random variable is smaller than a given
value and vice versa. We indicate two
computational methods: one uses
Microsoft Excel functions, while the other
is based on the traditional approach of
standardizing a normal random variable.
Given a r.v. X that is N(µ, σ), we often
face two problems.
© 2002 Thomson / South-Western
Slide 6-6
The Normal Distribution
Problem 1: Given any number x, find a
probability p = P{X ≤ x}.
Method 1. Use the Microsoft Excel
function NORMDIST:
p = NORMDIST(x, µ, σ, True).
© 2002 Thomson / South-Western
Slide 6-7
The Normal Distribution
Problem 1: Given any number x, find a
probability p = P{X ≤ x}.
Method 2. Transform the random variable
X and the number x into a new random
variable Z and number z as:
𝑥−𝜇
𝑍 = 𝑋−𝜇
and
𝑧
=
𝜎
𝜎
Then Z is also normally distributed with
mean 0 and a standard deviation 1.
© 2002 Thomson / South-Western
Slide 6-8
The Normal Distribution
Problem 1:
Method 2. (continued) That is, Z = N(0, 1),
which is called “standard normal” random
variable. Clearly
𝑝=𝑃 𝑋≤𝑥 =𝑃 𝑍≤𝑧
which can be read from the table of
cumulative distribution of the standard
normal r.v. For negative values of z,
notice by symmetry that
𝑃 𝑍 ≤ 𝑧 = 𝑃 𝑍 ≥ −𝑧 = 1 − 𝑃 𝑍 ≤ −𝑧
© 2002 Thomson / South-Western
Slide 6-9
The Normal Distribution
Problem 2:
Conversely, given any probability p, find a
number x, such that P{X ≤ x} = p.
Method 1. Use the Microsoft Excel
function NORM.INV:
x = NORM.INV(p, µ, σ)
© 2002 Thomson / South-Western
Slide 6-10
The Normal Distribution
Problem 2:
Method 2. Transform the random variable
X and the number x into their “standard”
counterparts Z and z as described above.
Given p, read z backwards from the table
such that P{Z ≤ z} = p and find the
quantity x by transforming back:
x = µ + zσ.
© 2002 Thomson / South-Western
Slide 6-11
Discussion Problem W03-02
•
Assume that weekly demand for phones at B&M Office
Supplies is normally distributed and independent across
weeks, with a mean of 2,500 and a standard deviation of
500. The manufacturer takes two weeks (lead time) to fill an
order placed by the B&M manager.
Copyright © 2016 Pearson Education, Inc.
12 – 12
Discussion Problem W03-02
a) The store manager currently orders 10,000 phones when
the inventory on hand drops to the Reorder Point (ROP) =
6,000. What is the probability that demand during lead
time (ddlt) does not exceed ROP = 6,000? That is, what is
the probability of no stock-out?
b) The store manager orders 10,000 phones when the
inventory on hand drops to ROP. The probability that
demand during lead time (ddlt) does not exceed ROP is
required to be at least 90%. What is the ROP?
Copyright © 2016 Pearson Education, Inc.
12 – 13
Normal distribution
Generate Normal Distribution:
x = NORM.INV(RAND(), µ, σ)
0.918842
0.395963
-0.79772
0.11585
0.987444
-0.24365
-0.71719
-0.74743
2.297748
1.169751
-1.21575
0.663374
0.470682
-1.16578
-0.77616
2.033189
-0.44258
0.727747
-0.09513
-1.293
0.88108
-0.91086
-0.16578
-0.31745
0.514011
1.505128
-0.44205
1.003868
-0.26488
0.309634
-1.55528
-0.27688
1.318288
-1.48123
0.428877
1.039995
-1.50424
-0.24944
1.112608
-0.90563
0.22384
1.134955
-1.90455
0.051121
-0.63878
-0.03582
0.147168
1.032384
0.763318
-1.58178
0.190792
0.116342
0.299409
-0.35769
0.020187
-1.70079
1.54783
0.523125
-0.67707
-0.40655
-3.19294
0.24598
-0.62806
-1.56228
-2.02277
-0.4383
1.002191
0.753205
-0.47117
1.479776
-0.05458
-2.40283
0.587668
-0.06385
1.013893
-0.14877
0.821971
0.447103
0.662095
-0.18641
-1.03276
-0.79103
0.245152
1.432146
-0.2499
-0.17436
-0.14949
0.79584
-0.67783
-1.53133
0.272352
-0.99651
1.039476
-0.07641
0.020781
0.223408
1.827398
-0.72093
0.476805
-3.11503
Normal distribution
Generate Normal Distribution:
x = NORM.INV(RAND(), µ, σ)
Normal distribution
How can we check if the distribution is
normal?
( http://www.engr.mun.ca/~ggeorge/4421/demos/NormPlot.html )
(The data should all be in one column.)
Load the Analysis Toolpak. Under the Tools
menu, choose Data Analysis, and
then Regression.
Normal distribution
How can we check if the distribution is
normal?
( http://www.engr.mun.ca/~ggeorge/4421/demos/NormPlot.html )
Follow the directions given in the dialog box:
1. Enter values for the Input Y Range. The
Input Y Range contains the data for which
you want the probability plot.
Normal distribution
How can we check if the distribution is
normal?
( http://www.engr.mun.ca/~ggeorge/4421/demos/NormPlot.html )
Follow the directions given in the dialog box:
2. Enter values for the Input X Range. These
are irrelevant in this case. We are only
interested in the Normal Probability Plot
option.
Normal distribution
How can we check if the distribution is
normal?
( http://www.engr.mun.ca/~ggeorge/4421/demos/NormPlot.html )
Follow the directions given in the dialog box:
3. Check the Normal Probability
Plots option. Click OK. Excel creates a
normal probability plot.
Normal distribution
How can we check if the distribution is
normal?
( http://www.engr.mun.ca/~ggeorge/4421/demos/NormPlot.html )
Follow the directions given in the dialog box:
4. Click on the newly created chart.
Under Chart in the menu, choose Add
Trendline. Under the Type tab, choose
the linear option.
Normal distribution
How can we check if the distribution is
normal?
( http://www.engr.mun.ca/~ggeorge/4421/demos/NormPlot.html )
Follow the directions given in the dialog box:
5. Under the Options tab, check Display Rsquared value on chart. The square root of
the R-squared value is the correlation
value.
Normal distribution
How can we check if the distribution is
normal?
( http://www.engr.mun.ca/~ggeorge/4421/demos/NormPlot.html )
0.918842
-1.21575
0.88108
-1.55528
0.22384
0.190792
-3.19294
-0.05458
-1.03276
0.272352
0.395963
0.663374
-0.91086
-0.27688
1.134955
0.116342
0.24598
-2.40283
-0.79103
-0.99651
-0.79772
0.470682
-0.16578
1.318288
-1.90455
0.299409
-0.62806
0.587668
0.245152
1.039476
0.11585
-1.16578
-0.31745
-1.48123
0.051121
-0.35769
-1.56228
-0.06385
1.432146
-0.07641
0.987444
-0.77616
0.514011
0.428877
-0.63878
0.020187
-2.02277
1.013893
-0.2499
0.020781
-0.24365
2.033189
1.505128
1.039995
-0.03582
-1.70079
-0.4383
-0.14877
-0.17436
0.223408
-0.71719
-0.44258
-0.44205
-1.50424
0.147168
1.54783
1.002191
0.821971
-0.14949
1.827398
-0.74743
0.727747
1.003868
-0.24944
1.032384
0.523125
0.753205
0.447103
0.79584
-0.72093
2.297748
-0.09513
-0.26488
1.112608
0.763318
-0.67707
-0.47117
0.662095
-0.67783
0.476805
1.169751
-1.293
0.309634
-0.90563
-1.58178
-0.40655
1.479776
-0.18641
-1.53133
-3.11503
Normal distribution
Normal Probability Plot
3
R² = 0.9302
2
1
0
Y
0
20
40
60
-1
-2
-3
-4
Sample Percentile
80
100
120
Discussion Problems W05-01
Check if the 100 numbers in Excel
Worksheet data of normalPlot.xlsx are
normally distributed.
0.918842
-1.21575
0.88108
-1.55528
0.22384
0.190792
-3.19294
-0.05458
-1.03276
0.272352
0.395963
0.663374
-0.91086
-0.27688
1.134955
0.116342
0.24598
-2.40283
-0.79103
-0.99651
-0.79772
0.470682
-0.16578
1.318288
-1.90455
0.299409
-0.62806
0.587668
0.245152
1.039476
0.11585
-1.16578
-0.31745
-1.48123
0.051121
-0.35769
-1.56228
-0.06385
1.432146
-0.07641
0.987444
-0.77616
0.514011
0.428877
-0.63878
0.020187
-2.02277
1.013893
-0.2499
0.020781
-0.24365
2.033189
1.505128
1.039995
-0.03582
-1.70079
-0.4383
-0.14877
-0.17436
0.223408
-0.71719
-0.44258
-0.44205
-1.50424
0.147168
1.54783
1.002191
0.821971
-0.14949
1.827398
-0.74743
0.727747
1.003868
-0.24944
1.032384
0.523125
0.753205
0.447103
0.79584
-0.72093
2.297748
-0.09513
-0.26488
1.112608
0.763318
-0.67707
-0.47117
0.662095
-0.67783
0.476805
1.169751
-1.293
0.309634
-0.90563
-1.58178
-0.40655
1.479776
-0.18641
-1.53133
-3.11503
More about normal distribution
(Spherically Uniform)
How can we pick a set of random points
uniformly distributed on the unit circle x12 +
x22=1?
More about normal distribution
(Spherically Uniform)
How can we generate uniformly distributed
points on the surface of the 3-d unit sphere x2
+ y2 + z2 = 1?
More about normal distribution
(Spherically Uniform)
• A standard method is to generate three
standard normals and construct a unit vector
from them. That is, when Xi ∼ N(0,1) and
λ2=X12 + X22+X32, then (X1/λ,X2/λ,X3/λ) is
uniformly distributed on the sphere. This
method works well for d-dimensional
spheres, too.
More about normal distribution
(Spherically Uniform)
Here is a picture of 100 independent draws from a uniform
spherical distribution obtained with the method:
More about normal distribution
(Spherically Uniform)
Spherical Uniform Distribution:
• How can we pick a set of random points uniformly
distributed on the 4-dimensional unit sphere x12 +
x22 + x32 + x42 =1?
Discussion Problem W05-02
Generate 100 random points (x1, x2, x3, x4) uniformly
distributed on the 4-dimensional unit sphere x12 + x22
+ x32 + x42 =1.
Chi-Square Distribution
• In probability theory and statistics, the chisquared distribution with k degrees of
freedom is the distribution of a sum of the
squares of k independent standard normal
random variables.
Discussion Problem W05-03
• A student claims that the 20
points on the right are
uniformly distributed on the
unit sphere. Check if his
claim is true. Use an Excel
function
CHISQ.INV(RAND(),k) to
scale the points on the unit
sphere back to normal.
ID
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
x1
0.430004
-0.02946
0.229287
-0.17224
-0.49227
-1.04505
1.189759
0.2092
-0.15866
-0.4369
0.443128
-0.44789
-0.28041
0.611842
-0.64634
-0.23787
-0.92584
0.078051
-0.71522
-0.48723
x2
-0.90149
0.091992
0.086981
-0.02726
0.340813
-0.33236
-0.36662
0.046161
0.494648
-0.55992
0.126155
-0.33003
0.097483
-0.70488
0.227253
0.217872
0.067467
0.087426
-0.41675
-0.4449
x3
-0.04914
0.662165
0.324414
0.086176
0.492164
-0.84766
-0.74931
-0.11354
-0.2732
0.266089
-0.358
-0.19669
0.00271
0.289633
-0.3257
-0.58871
0.430977
-0.12261
-0.27674
0.662477
Independent Normal Random
Variables
If X and Y are independent random variables
that are normally distributed, then their sum is
also normally distributed. That is, if
𝑋~𝑁 𝜇𝑋 , 𝜎𝑋2
𝑌~𝑁 𝜇𝑌 , 𝜎𝑌2
𝑍 = 𝑋 + 𝑌,
then
𝑍~𝑁 𝜇𝑋 + 𝜇𝑌 , 𝜎𝑋2 + 𝜎𝑌2 .
© 2002 Thomson /
South-Western
Slide 6-33
Independent Normal Random
Variables
This means that the sum of two independent
normally distributed random variables is
normal, with its mean being the sum of the
two means, and its variance being the sum of
the two variances (i.e., the square of the
standard deviation is the sum of the squares of
the standard deviations).
© 2002 Thomson /
South-Western
Slide 6-34
PERT Application of normal distribution and independence
Program Evaluation and Review Technique
(www.se.cuhk.edu.hk/~seem3530/files/ProjMgt-IA-PERT.ppt)
SHOPPING MALL RENOVATION
Discussion Problem W05-04
The durations of activities A, B, C, and D are independent and
normally distributed with [mean, standard deviation] in
the process flow chart below.
What is the probability to complete the project within 17
weeks?
PERT
SEEM 3530
36
Example: Modified Calculations
▪
PERT
Then the durations of the two paths are
normally distributed as follows:
length (A-B) = X1 ~ N(17, 3.61)
length (C-D) = X2 ~ N(16, 3.35)
SEEM 3530
37
The Probability Density Functions
PERT
SEEM 3530
38
Project Completion Probabilities
▪
The project can be completed in 17 weeks only if both (A-B) and
(C-D) are completed within that time. The probabilities for the
two paths to be completed in that time are given below:
17-17
P(X1 17) = P(Z ----------- ) = P(Z 0)=0.5
3.61
17-16
P(X2 17) = P(Z ----------- ) = P(Z 0.299)=0.62
3.35
▪
Thus, the probability of completing the project within 17 weeks is
P(X 17) = P(X1 17) P(X2 17) = (0.5)(0.62) = 0.31 = 31 %.
PERT
SEEM 3530
39
Project Completion Probabilities
▪
▪
▪
Assume there are n paths, with completion
times X1, X2, …, Xn. Then, the probability of
completing the project is
P(X T) = P(X1 T) P(X2 T) … P(Xn T)
Assume that the paths are statistically
independent (i.e. the time to traverse each
path in the network is independent of what
happens on the other paths).
Although this additional assumption is rarely
true in practice, empirical evidence suggests
that good results can be obtained.
PERT
SEEM 3530
40
PERT Application of normal distribution and independence
Program Evaluation and Review Technique
(MBPF)
WONDER SHED INC.
Process Flow Time
Wonder Shed Inc. is a manufacturer of storage
sheds. The manufacturing process involves the
procurement of sheets of steel that will be used
to form both the roof
and the base of each
shed.
42
Process Flow Time
The first step involves separating the material
need for the roof from that needed for the base.
Then the roof and the base can be fabricated in
parallel, or simultaneously. Roof fabrication
involves first punching and then forming the
roof to shape. Base fabrication entails the
punching-and-forming process plus a
subassembly operation.
43
Process Flow Time
Fabricated roofs and bases are then assembled
into finished sheds that are subsequently
inspected for quality assurance. A list of
activities needed to fabricate a roof, fabricate a
base, and assemble a shed is given in Table 4.2.
a flowchart of the process is shown in Figure 4.1.
44
Flow time and critical paths
45
Process Flow Time
Table 4.2 adds the mean duration, called flow
time, of each activity.
See that the flowchart (Figure 4.1) shows that
two paths connecting the beginning and the end
of the process
– Path 1 (roof): Start→1 → 3 → 5 → 7 → 8 → End
• 120 minutes = 20 + 25 + 20 + 15 + 40
– Path 2 (base): Start →1 →2 →4 →6 →7 →8 →End
• 150 minutes = 20 + 35 + 10 + 30 + 15 + 40
46
Process Flow Time
Assume that the duration of each activity is
independent and normally distributed with the
mean and the variance in the following table:
Activity
Mean Time
Variance
1
20
9
2
35
36
3
25
16
4
10
4
5
20
10
6
30
28
7
15
7
8
40
50
47
Process Flow Time
We also assume that Path 1 and Path 2 are
independent. What is the probability that both
of them finish within 140 minutes?
Activity
Mean Time
Variance
1
20
9
2
35
36
3
25
16
4
10
4
5
20
10
6
30
28
7
15
7
8
40
50
48
Process Flow Time
• The mean time and the variance of Path 1 are
– Path 1 (roof): Start→1 → 3 → 5 → 7 → 8 → End
• 120 minutes = 20 + 25 + 20 + 15 + 40
• 92 minutes2 = 9 + 16 + 10 + 7 + 50
• The duration of Path 1 is N(µ = 120, σ2 = 92).
49
Process Flow Time
• The mean time and the variance of Path 2 are
– Path 2 (base): Start →1 →2 →4 →6 →7 →8 →End
• 150 minutes = 20 + 35 + 10 + 30 + 15 + 40
• 134 minutes2 = 9 + 36 + 4 + 28 + 7 + 50
• The duration of Path 2 is N(µ = 150, σ2 = 134).
50
Process Flow Time
• The duration of Path 1 is N(µ = 120, σ2 = 92).
• The duration of Path 2 is N(µ = 150, σ2 = 134).
P[X1 ≤ 140] = NORMDIST(140,120,SQRT(92),1)
P[X2 ≤ 140] = NORMDIST(140,150,SQRT(134),1)
What is the probability that both of them finish
within 140 minutes?
P[X1 ≤ 140, X2 ≤ 140] = P[X1 ≤ 140] * P[X2 ≤ 140]
51
Process Flow Time
▪
▪
▪
We assumed that the paths are statistically
independent (i.e. the time to traverse each path in the
network is independent of what happens on the other
paths).
Strictly speaking, this additional assumption is hardly
true because activities 1, 7, and 8 belong to both of
Paths 1 and 2,
Although this additional assumption is rarely true in
practice, empirical evidence suggests that good results
can be obtained.
PERT
SEEM 3530
52
Discussion Problem W05-05
Wonder Shed Inc. is a manufacturer of storage
sheds. The manufacturing process involves the
procurement of sheets of steel that will be used
to form both the roof
and the base of each
shed.
53
Discussion Problem W05-05
The first step involves separating the material
need for the roof from that needed for the base.
Then the roof and the base can be fabricated in
parallel, or simultaneously. Roof fabrication
involves first punching and then forming the
roof to shape. Base fabrication entails the
punching-and-forming process plus a
subassembly operation.
54
Discussion Problem W05-05
Fabricated roofs and bases are then assembled
into finished sheds that are subsequently
inspected for quality assurance. A list of
activities needed to fabricate a roof, fabricate a
base, and assemble a shed is given in Table 4.2.
A flowchart of the process is shown in Figure
4.1.
55
Flow time and critical paths
56
Discussion Problem W05-05
Assume that the duration of each activity is
independent and normally distributed with the
mean and the variance in the following table:
Activity
Mean Time
Variance
1
20
9
2
35
36
3
25
16
4
10
4
5
20
10
6
30
28
7
15
7
8
40
50
57
Discussion Problem W05-05
We also assume that Path 1 and Path 2 are
independent. What is the probability that both
of them finish within 140 minutes?
Activity
Mean Time
Variance
1
20
9
2
35
36
3
25
16
4
10
4
5
20
10
6
30
28
7
15
7
8
40
50
58
Application of Independent Normal Distributions
IMPACT OF AGGREGATION
ON INVENTORY
Impact of Aggregation
on Inventory
A BMW dealership has k = 4 retail outlets serving the
entire Chicago area (disaggregate option). Weekly
demand at each outlet is normally distributed, with a
mean of D = 25 cars and a standard deviation of σD = 5.
The lead time for replenishment from the manufacturer
is L = 2 weeks. The outlet manager orders when the
inventory on hand drops to the Reorder Point (ROP).
Copyright © 2016 Pearson Education, Inc.
12 – 60
Impact of Aggregation
on Inventory
Each outlet covers a separate geographic area, and the
demand of each outlet is independent of the other. The
dealership is considering the possibility of replacing the
four outlets with single large outlet (aggregate option).
Copyright © 2016 Pearson Education, Inc.
12 – 61
Impact of Aggregation
on Inventory
Assume that the demand in the central outlet is the
sum of the demand across all four areas. The
probability of demand during lead time does not
exceed the reorder point is required to be at least 90%.
a) What is the reorder point of each outlet in
disaggregate option?
b)What is the reorder point of the central outlet in
aggregate option?
Copyright © 2016 Pearson Education, Inc.
12 – 62
Impact of Aggregation
on Inventory
a) What is the reorder point of each outlet in
disaggregate option?
Let X be the random variable of demand during lead
time for one outlet and let X1 and X2 be the random
variables of demand for the 1st week and the 2nd week.
Then X = X1 + X2. The average demand during lead
time (2 weeks) is E[X] = D + D = 25 + 25 = 50 and the
variance is V[X] = σ2 + σ2 = 25 + 25 = 50.
Copyright © 2016 Pearson Education, Inc.
12 – 63
Impact of Aggregation
on Inventory
a) What is the reorder point of each outlet in disaggregate
option?
𝑃 𝑋 < 𝑅𝑂𝑃 = 𝑃 𝑍 < 𝑅𝑂𝑃−𝐸[𝑋]
𝑉[𝑋]
= 𝑃 𝑍 < 𝑅𝑂𝑃−50
50
=𝐹
Therefore,
𝑅𝑂𝑃−50
50
𝑅𝑂𝑃−50
50
= 0.90
= z0.90
Or, ROP = NORM.INV(0.90,50,SQRT(50)) = 59.06193802
Copyright © 2016 Pearson Education, Inc.
12 – 64
Impact of Aggregation
on Inventory
b) What is the reorder point of the central outlet in
aggregate option?
Let Y be the random variable of demand during lead
time for the central outlet. The average demand during
lead time (2 weeks) is E[Y] = 4 * 50 = 200 and the
variance is V[Y] = 4 * 50 = 200. Let cROP denote the
reorder point of the central outlet.
Copyright © 2016 Pearson Education, Inc.
12 – 65
Impact of Aggregation
on Inventory
b) What is the reorder point of the central outlet in
aggregate option?
𝑃 𝑌 < 𝑐𝑅𝑂𝑃 = 𝑃 𝑍 < 𝑐𝑅𝑂𝑃−𝐸[𝑌]
𝑉[𝑌]
= 𝑃 𝑍 < 𝑐𝑅𝑂𝑃−200
=𝐹
Therefore,
𝑐𝑅𝑂𝑃−200
200
200
𝑐𝑅𝑂𝑃−200
=
200
0.90
= z0.90
Or, cROP = NORM.INV(0.90,200,SQRT(200))
= 218.1239 < 236.2478 = 4 * 59.06193802 = 4 * ROP
Copyright © 2016 Pearson Education, Inc.
12 – 66
Discussion Problem W05-06
A BMW dealership has k = 4 retail outlets serving the
entire Chicago area (disaggregate option). Weekly
demand at each outlet is normally distributed, with a
mean of D = 25 cars and a standard deviation of σD = 5.
The lead time for replenishment from the manufacturer
is L = 2 weeks. The outlet manager orders when the
inventory on hand drops to the Reorder Point (ROP).
Copyright © 2016 Pearson Education, Inc.
12 – 67
Discussion Problem W05-06
Each outlet covers a separate geographic area, and the
demand of each outlet is independent of the other. The
dealership is considering the possibility of replacing the
four outlets with single large outlet (aggregate option).
The dealership is considering the possibility of replacing
the four outlets with a single large central outlet
(aggregate option).
Copyright © 2016 Pearson Education, Inc.
12 – 68
Discussion Problem W05-06
Assume that the demand in the central outlet is the
sum of the demand across all four areas. The
probability of demand during lead time does not
exceed the reorder point is required to be at least 90%.
a) What is the reorder point of each outlet in
disaggregate option?
b)What is the reorder point of the central outlet in
aggregate option?
Copyright © 2016 Pearson Education, Inc.
12 – 69
Normal Approximation of the
binomial distribution
For large n (say n > 20) and p not too near 0
or 1 (say 0.05 < p < 0.95) the distribution
approximately follows the Normal
distribution. This can be used to find binomial
probabilities. If X ~ binomial (n, p) where n
> 20 and 0.05 < p < 0.95 then approximately
X has the Normal distribution with mean E(X)
= np and variance V(X) = np(1 – p).
© 2002 Thomson /
South-Western
Slide 6-70
Normal Approximation of Binomial:
Parameter Conversion
• Conversion equations
= n p
= n pq
• Conversion example:
Given that X has a binomial distribution
, find
P( X 25| n = 60 and p =. 30 ).
= n p = (60 )(. 30 ) = 18
= n p q = (60 )(. 30 )(. 70 ) = 3. 55
© 2002 Thomson / South-Western
Slide 6-71
Normal Approximation of Binomial:
Interval Check
3 = 18 3(355
. ) = 18 10.65
− 3 = 7.35
+ 3 = 28.65
0
10
20
© 2002 Thomson / South-Western
30
40
50
60
n
70
Slide 6-72
Normal Approximation of Binomial:
Correcting for Continuity
Values
Being
Determined
Correction
X
X
X
X
X
X
+.50
-.50
-.50
+.05
-.50 and +.50
+.50 and -.50
© 2002 Thomson / South-Western
The binomial probability ,
P( X 25| n = 60 and p =. 30)
is approximated by the normal probability
P(X 24.5| = 18 and = 3. 55).
Slide 6-73
Normal Approximation of Binomial:
Graphs
0.12
0.10
0.08
0.06
0.04
0.02
0
6
8
10 12 14 16 18 20 22 24 26 28 30
© 2002 Thomson / South-Western
Slide 6-74
Normal Approximation of Binomial:
Computations
X
P(X)
25
26
27
28
29
30
31
32
33
Total
0.0167
0.0096
0.0052
0.0026
0.0012
0.0005
0.0002
0.0001
0.0000
0.0361
© 2002 Thomson / South-Western
The normal approximation,
P(X 24.5| = 18 and = 355
. )
24.5 − 18
= P Z
355
.
= P( Z 183
. )
=.5 − P( 0 Z 183
. )
=.5−.4664
=.0336
Slide 6-75
3-10 Normal Approximation to the Binomial
and Poisson Distributions
Normal Approximation to the Binomial
Discussion Problem W05-07-(a, b)
Fill in the blank rectangles:
a)
b)
3-10 Normal Approximation to the Binomial
and Poisson Distributions
Normal Approximation to the Poisson
3-10 Normal Approximation to the Binomial
and Poisson Distributions
Normal Approximation to the Poisson
Example 3-36: Water Contaminants
3-10 Normal Approximation to the Binomial
and Poisson Distributions
Normal Approximation to the Poisson
Example 3-36: Water Contaminants (continued)
Discussion Problem W05-08
Normal Approximation to the Poisson
Example 3-36: Water Contaminants
Estimate the probability based on Normal Approximation.
Discussion Problem W05-01
The durations of activities A, B, C, and D are independent and
normally distributed with [mean, standard deviation) in
the process flow chart below.
What is the probability to complete the project within 17
weeks?
(mean, standard deviation)
60
A
[9,3)
(8,21
с
D
[10,3]
[6,1.5]
3
PERT
SEEM 3530
1
Discussion Problem W05-02
Wonder Shed Inc. is a manufacturer of storage
sheds. The manufacturing process involves the
procurement of sheets of steel that will be used
to form both the roof
and the base of each
shed.
2
Discussion Problem W05-03
A BMW dealership has k = 4 retail outlets serving the
entire Chicago area (disaggregate option). Weekly
demand at each outlet is normally distributed, with a
mean of D = 25 cars and a standard deviation of op = 5.
The lead time for replenishment from the manufacturer
is L = 2 weeks. The outlet manager orders when the
inventory on hand drops to the Reorder Point (ROP).
Copyright © 2016 Pearson Education, Inc.
12-8
Discussion Problem W05-03
Each outlet covers a separate geographic area, and the
demand of each outlet is independent of the other. The
dealership is considering the possibility of replacing the
four outlets with single large outlet (aggregate option).
The dealership is considering the possibility of replacing
the four outlets with a single large central outlet
(aggregate option).
Copyright © 2016 Pearson Education, Inc.
12-9
Discussion Problem W05-03
Assume that the demand in the central outlet is the
sum of the demand across all four areas. The
probability of demand during lead time does not
exceed the reorder point is required to be at least 90%.
a) What is the reorder point of each outlet in
disaggregate option?
b)What is the reorder point of the central outlet in
aggregate option?
Copyright © 2016 Pearson Education, Inc.
12-10
Purchase answer to see full
attachment